A road safety scheme on the existing A1: closing all the gaps in the central reservation (around 100), a continuous central safety barrier, four new flyover junctions (Listullycurran Road, Gowdystown Road, Skeltons Road/Drumneath Road and Waringsford Road), a northbound on-slip at Castlewellan Road in Banbridge, a link road to Milebush Road in Dromore, and closing or converting side roads and private accesses to left-in, left-out only. Up to 40,000 vehicles a day use parts of the route.
The Outline Business Case was approved on 9 November 2026 with an estimated cost of £125m to £150m, and the Vesting Order to buy the land was made on 13 November 2026. The main construction contract has not been awarded: the Department paused decisions while the A5 case was in the courts, and is now starting procurement for a site clearance contract.