A 2.1km single-carriageway bypass with overtaking lanes, two roundabouts and new bridges over the River Erne and River Sillees, plus 3.5km of footway and cycleway. It is meant to take through traffic on the A4 out of Enniskillen town centre.
Statutory Orders were approved in 2021, funding was agreed in 2024 and tenders have been received, but the contract has not been awarded: DfI deferred the award after the June 2025 A5 High Court ruling, and a tenderer has challenged the procurement in the High Court (writ of 13 January 2026, disclosed in October 2026).