Phase 5.1 of the redevelopment of Altnagelvin Hospital, to move inpatients out of the 1960 Tower Block. Its centrepiece is the North Wing: six 24-bed wards of single en suite rooms and a new main hospital entrance, built beside the Tower Block after enabling works including a multi-storey car park. The Trust's finance reports call the whole phase 'Altnagelvin 5.1 - Tower Block Development', which is the project the Audit Office lists as 'Altnagelvin Hospital Tower Block'. Later work in the phase refurbishes parts of the Tower Block, including a new children's department.
The North Wing opened in 2020, a year late. The wider phase was still under way in October 2024 (a new paediatric wing), and the Audit Office expected it to finish in September 2026, ten years after the original date; we have not found confirmation that it has.