New-Bridge Integrated College

A new post-primary school building and sports hall for New-Bridge Integrated College, built in phases on the existing site while the school stayed open, with new pitches on neighbouring land. It is one of the shared and integrated education schemes paid for from the UK Government's Fresh Start capital funding.

Built between January 2023 and September 2026 and officially opened in October 2026, about a year later than the Audit Office was told in 2023; the Department gives the cost as £27.5m.