About 8km of flood defences (embankments, walls and sheet-pile or piled walls) at 21 sites around Portadown, designed to protect over 380 homes and businesses from a river flood with a 1% chance of happening in any year, with an allowance for climate change. Portadown has flooded regularly over the last 30 to 40 years, most recently in autumn 2023.
Procurement of a contractor began in October 2025 and advance works and site clearance started in January 2026. Main construction was due to start in autumn or winter 2026 and take about six years. The estimate has risen from under £8m at feasibility stage to about £60m.