A new 10-floor regional children’s hospital with 155 beds, 10 theatres and an emergency department, replacing the Royal Belfast Hospital for Sick Children, parts of which date from 1932. It is one half of the Executive’s Maternity and Children’s Hospital flagship project.
Under construction since March 2025 with a programmed completion of March 2030, but in September 2026 Belfast Trust’s board was told of a delay of about 8 months and possible cost increases from water-system and fire-stopping issues that may use up the whole £50m contingency. Revised costs and dates are expected in the New Year.