A new energy centre to supply heat and power to the Royal Victoria Hospital site, replacing the existing boiler plant. It was to include steam boilers, combined heat and power units and high voltage generators, and was meant to be running 18 months before the new Regional Children's Hospital is handed over.
Paused since February 2024 after the preferred tender came in at four times the approved business case cost. The Audit Office's last estimate was £159.5m against £42.5m, the largest percentage overrun in its list. About £9.5m had been spent by December 2024; an interim solution is to supply the site, including the new children's hospital, for around 10 years.