Ulster University Belfast campus (Greater Belfast Development)
Ulster University's move of most of its Jordanstown campus into a greatly expanded Belfast city centre campus: refurbishment and construction of four blocks (BA, BB, BC and BD), later extended to work around Frederick Street, other buildings and a car park. The final phase, a 75,000 square metre building, opened in September 2022. The university led it, paying mostly from its own reserves and government loans, so it is not a government building, but public grants and loans of more than £200m went into it.
Opened in full in September 2022, four years later than planned. The Audit Office puts the final cost at £357.8m in one part of its 2024 report and £364m in another, against £254m in the 2010 business case.
Status: Open
Led by: Ulster University, with grants and loans through the Department for the Economy
Where: York Street, Belfast city centre
First published cost: £254m (Mar 2010, Audited)
Latest cost: £357.8m (27 Feb 2024, Audited)
Spent so far: £343m (to Sep 2023, Audited)
Timeline
Mar 2010: Business case approved
Jun 2013: Construction starts
11 Feb 2014: £150m European Investment Bank loan signed
Mar 2015: Phase two contract awarded
Mar 2016: Basement defects delay the work
Feb 2017: European Investment Bank withdraws its loan
Mar 2018: Lagan Construction goes into administration
18 Dec 2019: Audit Office: £363.9m and three years late